Etowa County Residents Ecstatic! Wind Leases Terminated, Wind Pushers Leave Town!

Wind energy company pulling out of Cherokee, Etowah County projects, opposition says

 
on August 19, 2014 
 
Oklahoma wind farm.jpg

CENTRE, Alabama — Groups opposed to a proposed wind farm project in Cherokee and Etowah counties say the company behind the development has informed them that it will not be building a wind farm in Alabama.

According to a document filed July 9 in Cherokee County Probate Court, Pioneer Green Energy President Andrew Bowman signed a memorandum terminating a lease to about 1,889 acres of property, slated to be developed for the project. 

Mitzi Gibbs Eaker, with No Wind Alabama, said a similar agreement was signed in Etowah County.

Charlie Stewart, the attorney for Pioneer Green, had no comment beyond the filed documents. Company officials referred media inquiries to Stewart.

Pioneer Green Energy announced last year it planned to develop wind energy projects in Cherokee and Etowah counties, and said land leases had already been secured.

Five Cherokee County residents filed suit in an attempt to stop the development, and a group of Etowah County residents also filed suit, opposing the project in their county.

Pioneer Green later announced the $40 million Cherokee County project, which called for seven to eight turbines, probably would not begin construction until 2015. Company officials said the larger Etowah County project, which projected 30 to 45 turbines costing $160 million, probably would begin no earlier than the end of 2015.

Residents said they opposed the project for several reasons – among them environmental and property value concerns, noise, the change to the landscape and the long-term prospects of the development. “No Wind Alabama” took its name from what it said was the reason why wind developments have largely avoided the South -because of a lack of wind energy to supply sufficient power.

Pioneer Green officials countered that wind energy technology has improved to the point where wind could be used in areas earlier thought unable to support it.

Ginny Shaver, a Leesburg resident who opposed the project, said the turning point was in getting legislation passed calling for design specifications, setbacks and other regulations.

“When we got the local bills, that was the winning moment in my eyes,” Shaver said. “We had so much support from residents, in our groups, and it was just good, old fashioned lobbying from the people. From there, it was contacting legislators, making trips to Montgomery. It was literally a David versus Goliath thing. We didn’t have money, but we had people, and it was just a question of getting information out and educating folks.”

Eaker, who said she opposed the project because it would have negatively impacted her parents’ property in Etowah County, said she never felt confident of the outcome until attorneys informed her of the documents today.

“The residents are ecstatic that they can get back to their lives as normal,” she said. “We never felt confident. We always wondered what they had in their back pocket. It was only when we learned that the leases had been terminated that we knew it was really over.” 

 
 

Uncommonly Good News….I would Love to Hear Much More Like It!

Contract scrapped

By Leith Dunick, tbnewswatch.com

Streak of Green – Hair SalonHey Stylists! It’s time to go green! Looking for a F/T stylist to join our team in a very busy organic, eco friendly full service salonwww.streakofgreen.com

A spokeswoman for the Nor’Wester Mountain Escarpment Protection Committee says she’s ecstatic that Horizon Wind Inc.’s planned turbine farm in Thunder Bay might be dead in the water.

Irene Bond said she learned on Friday that the Ontario Power Authority had cancelled the Toronto-based company’s feed-in tariff contract, essentially ending the agreement to sell energy to the provincial grid. 

Bond said the news caught her off guard.

“If this is the news that will end this project, that the FIT contract is indeed cancelled for the whole project, yeah it is a surprise and a very welcome one,” she said.

“I’m just thrilled that this will finally be over. We’ve been at it for five years as a community grass-roots group to educate people about the destruction and the history of the land and that it deserves better than to be industrialized.”

The OPA confirmed the contract cancellation via email on Friday, citing project delays as the main reason for the decision.

“The Big Thunder Wind Park project was significantly delayed due to force majeure events,” OPA spokeswoman Mary Bernard said. “Under a FIT contract, either party to the contract has the right to terminate the contract if force majeure events delay a project past 24 months. The OPA terminated the Big Thunder Park project for this reason.”

According to Bernard, a force majeure is a stipulation in a contract that provides relief to a party when events beyond their control prevent them from fulfilling certain contractual obligations. But it also specifies a time limit to get things back on track.

“The OPA cannot provide details of the force majeure events due to confidentiality obligations under the contract,” Bernard said.

It’s unclear if there is an appeal process available to Horizon at this time.

Horizon Wind released a brief statement saying they have provided notice of dispute to the OPA on their decision to end the contract.

“Pending resolution of the disputed issues, Horizon Wind is evaluating its options,” the statement reads. 

The project was first approved by Thunder Bay city council in 2007.

A dispute with the city led to Horizon in 2010 filing a $126-million lawsuit against the municipality when council refused to approve certain turbine locations.

The city later backed down and the lawsuit was tossed.

More recently Fort William First Nation filed a judicial review against the Ministry of the Environment asking for all work on the project to stop until the community had been properly consulted.

The FWFN claim alleged the province failed to consult them about the project itself and the company’s 2013 renewable energy approval.

Fort William First Nation Chief Georjann Morriseau called it a great day, but said the band won’t drop any of its legal challenges until they’re 100 per cent certain the project won’t be completed. 

“It’s still slightly early for that,” Morriseau said. “Right now, today we’ve been working on trying to receive more confirmation on what this actually means for the project itself, for the REA application and process moving forward.

“Once we do receive that confirmation we’ll be sure to update both communities on the developments.” 

It’s not necessarily the end of the project, she cautioned. 

“It wouldn’t come as a surprise if there is an appeal,” she said, adding she thinks treaty rights must come first and be protected and will ultimately prevail.

City of Thunder Bay officials said they too are looking into the legal implications of the decision, after learning of it that morning.

“At this point we’re trying to understand what it means. We have a lease with Horizon, so I’ve asked our staff to look at it,” Commisso said, wary of speaking to specifics of the lease or whether or not he thinks it’s a good decision. 

Mayor Keith Hobbs had little to say.

“I have no comment at this time,” he said.

Minister of Natural Resources Bill Mauro said he was advised two or three days ago through the Ministry of Energy the contract was being terminated.

Mauro, a longtime opponent of the project, was coy in his reaction when asked Friday morning.

“My position on it has been well known,” Mauro said. “This is an OPA decision. The Ontario Power Authority has informed me … they’re not going through with the project and I think that we’re all going to move forward from there.”